Massachusetts SREC-II Application Timeline

Posted June 27th, 2018 by SRECTrade.

While the Solar Massachusetts Renewable Target (SMART) Program Effective Date is still to be announced by the Department of Energy Resources (DOER), the application timelines for SREC-II have been set.

As a reminder, the SMART Program Effective Date will be the deadline for facilities smaller than or equal to 25 kW DC to be interconnected and facilities larger than 25 kW DC to be mechanically complete. This means that documentation must be dated on or before the Effective Date, but applications can be submitted for some time after.

Facilities larger than 25 kW DC will have two weeks after the SMART Program Effective Date to submit their documentation demonstrating mechanical completion. Once granted, mechanically complete extensions are indefinite – facilities should simply submit their Permission to Operate (PTO) documents once they are received to complete their statement of qualification application.

Facilities smaller than or equal to 25 kW DC will have until November 15th to submit an application demonstrating authorization to interconnect. In other words, the PTO must be dated on or before the effective date, but the applications can be submitted to the DOER up through November 15th.

For more information please reference the DOER’s Current Status of the Solar Carve Out II Program page.

DOER Announces SMART Program Administrator & 100 MW RFP // SREC-II Deadline on March 31, 2018

Posted November 14th, 2017 by SRECTrade.

On November 13, 2017 the Department of Energy Resources (DOER) announced that CLEAResult, Inc. will be the Solar Program Administrator for Massachusetts’s SMART Program.

The Distribution Companies have developed a request for proposals (RFP) for approximately 100 MW of solar projects in their respective utility service territories. The Distribution Companies will be hosting a bidder’s conference on Friday, November 17, 2017 at 1:00 PM EST to provide additional information and answer questions. Written comments on the RFP will be accepted through November 20, 2017 at 12:00 PM EST and should be submitted to ma.smart@clearesult.com. Bidders can submit an application on CLEAResult’s application website from November 27, 2017 – December 5, 2017 at 5:00 PM EST.  Results will be announced by the DOER by January 11, 2018. These results will establish the Block 1 Base Compensation Rates under the SMART Program.

The full announcement by the DOER can be found here.

As a reminder, systems must be mechanically complete or commercially operational by March 31, 2018 in order to participate in SREC-II under the current SREC Factors. Factors will be further reduced after this date but will remain at 0.8 for systems less than or equal to 25 kW.

DOER Files SMART Program Emergency Regulation

Posted June 5th, 2017 by SRECTrade.

On Monday, June 5th, the MA Department of Energy Resources (DOER) filed an emergency regulation to implement the Solar Massachusetts Renewable Target (SMART) Program. The regulation is directed toward supporting the development of an additional 1,600 MW of solar energy generating facilities via a declining block program.

Although the emergency regulation takes effect immediately, it can only remain in effect for three months. The emergency regulation is a placeholder, pending a full rulemaking proceeding conducted by DOER, at which time the final program rules will be established. Following the conclusion of the DOER’s rulemaking process, the Department of Public Utilities (DPU) will need to conduct a proceeding for the DPU’s approval of the tariffs filed by the Electric Distribution Companies. Only after this rulemaking and proceeding take place will the SMART program be in effect. Accordingly, the SREC-II program remains in effect for all eligible solar facilities.

As a result of this implementation schedule, it is expected that solar facilities will be eligible to qualify for the SREC-II program through the end of Quarter 1, 2018.

For more information on the SMART program, please feel free to reference our last blog post on the topic here. The DOER’s official notice regarding this emergency regulation is available here.

DOER Announces Final SREC-II Factor Guidelines

Posted March 27th, 2017 by SRECTrade.

On Thursday, March 23rd the DOER provided an update on the finalized SREC-II program SREC Factors for projects over 25 kW that have not previously qualified for an SREC-II extension.

All SREC-II facilities that have a Statement of Qualification (SQA), but have not yet received an extension, will have their SQAs rejected. New applications may be submitted for these facilities, however, to seek an extension under these new guidelines. Any extension granted will be effective until March 31, 2018 at the following factors:

new-market-factors

Please note that SREC-II systems with a capacity equal to or less than 25 kW will still receive an SREC Factor of 0.8, so long as they receive their authorization to interconnect before the effective date of the SMART program.

Facilities eligible for the extension are those that have not already received either a mechanically complete or 50% construction cost extension; facilities that can demonstrate that they are mechanically complete or commercially operational by March 31, 2018 will receive their respective SREC Factor listed above.

DOER Announces Status of Next Generation Incentive Program and SREC-II Bridge

Posted January 24th, 2017 by SRECTrade.

This morning, the DOER provided an update on both the Next Generation Incentive Program and the transition between SREC-II and the new program.

Next Generation Incentive Program

The DOER  will present the final proposal for the design of the Next Generation Incentive Program at a public briefing on January 31, 2017. Per the DOER’s update, the “proposal will be used by DOER as the framework for the regulation to implement the program, which DOER plans to file in the coming weeks.”

SREC-II Transition

Due to the expected timeframe for the implementation of the Next Generation Incentive Program, the DOER is in the process of implementing interim measures to bridge the gap and ensure a smooth transition between SREC-II and the new program. The DOER will provide additional details regarding these interim measures in the January 31st meeting.

Information for the meeting is as follows:

Date: January 31, 2017
Time: 1:00-4:00PM
Location: Federal Reserve Building
Morris Auditorium
600 Atlantic Avenue

Boston, MA 02210

The Federal Reserve Building requires a list of all attendees in advance of the meeting. If you plan to attend the meeting, the DOER requests that you please fill out this form to RSVP by 5:00PM this Friday, January 27, 2017.

MA SREC-II Extension Webinar

Posted December 13th, 2016 by SRECTrade.

Earlier today, SRECTrade hosted a webinar covering the current state of the Massachusetts SREC-II program, key deadlines for qualifying systems under SREC-II, and SRECTrade application processes.

The application window is currently open for all MA systems, regardless of size, although qualification deadlines are approaching. Please feel free to reference SREC-II Extension Application Instructions HERE.

For access to the presentation slides, please click here: MA SREC-II Extension Webinar. To view a video recording of the webinar, please click the image below.

This document and recording is protected by copyright laws and contains material proprietary to SRECTrade, Inc. It or any components may not be reproduced, republished, distributed, transmitted, displayed, broadcast or otherwise exploited in any manner without the express prior written permission of SRECTrade, Inc. The receipt or possession of this document does not convey any rights to reproduce, disclose, or distribute its contents, or to manufacture, use, or sell anything that it may describe, in whole or in part. If consent to use these materials is granted, a link to the current version of this document on the SRECTrade website must be included for reference.

MA SREC-II Installer Webinar

Posted December 12th, 2016 by SRECTrade.

SRECTrade will be hosting a webinar this Tuesday, December 13th, at 2:00 PM EST. The webinar will cover the current state of the Massachusetts SREC-II program, key deadlines for qualifying systems under SREC-II, and SRECTrade application processes to consider as the program’s close approaches.

To attend the webinar click HERE to register. A recording will be made available on SRECTrade’s blog for those unable to attend.

MA DOER Announces Solar Credit Clearinghouse Auction Results

Posted July 29th, 2016 by SRECTrade.

Today, the Massachusetts Department of Energy Resources (DOER) announced that both of the 2015 Solar Carve-out (SREC-I) and Solar Carve-out II (SREC-II) auctions have fully cleared in the first round.

Preliminary results for the SREC-I auction included 41 unique bidders submitting a total bid volume of 49,886 – more than sufficient demand to clear the available auction volume of 1,898 SRECs. Similarly, the results for the SREC-II auction included 9 unique bidders submitting a total bid volume of 112,252, which cleared the available auction volume of 67,046 SREC-IIs.

SCCA Auction Results3

The DOER and EnerNOC continue to certify and finalize the auction results, and will publicize more details on the final results on the SREC-I and SREC-II auction webpages next week.

MA DOER Announces Preliminary 2017 Compliance Obligation

Posted July 25th, 2016 by SRECTrade.

Friday, July 22, 2016, the Massachusetts Department of Energy Resources (DOER) announced the preliminary 2017 Solar Carve-out (SREC-I) and Solar Carve-out II (SREC-II) Compliance Obligations and Minimum Standards. Customarily, the DOER estimates these values prior to administering the Solar Credit Clearinghouse Auction each year. The final 2017 Minimum Standards will be announced on or before August 30th, after both the SREC-I and SREC-II Auctions have concluded.

Solar Carve-out (SREC-I)

Notably, the DOER projects that the final 2017 Compliance Obligation for the SREC-I program will be approximately 783,181 MWhs and that the Minimum Standard will be approximately 1.6313%. These values will be increased to 785,077 MWhs and 1.6352%, respectively, if the SREC-I auction does not fully clear in the first two rounds. The 2017 Minimum Standard for load under contracts signed before June 28, 2013 will be 0.9861%.

The DOER published a resource outlining its calculation of the preliminary SREC-I Minimum Standard.

Preliminary 2017 Compliance Obligation SREC-I Table

Solar Carve-out II (SREC-II)

Regarding the SREC-II Program, the DOER established a baseline Compliance Obligation and Minimum Standard that would have applied to Retail Electricity Suppliers had the RPS Class I Emergency Regulation not been filed on April 8, 2016; these suppliers are exempt from any additional obligations resulting from the expansion of the SREC-II Program Capacity Cap.

To calculate this baseline Minimum Standard, the DOER first determined the expected MWh/year that would have resulted had the SREC-II Program Capacity Cap remained 947 MW by:

  1. Identifying the percentage shares of MW currently qualified under each SREC-II Market Sector;
  2. Multiplying these percentages by the original 947 MW SREC-II Program Capacity Cap;
  3. Multiplying these totals by (1) their respective SREC Factors, (2) a 13.51% expected capacity factor, and (3) 8,760 hours/year.

The DOER then summed these values and combined the auction volume and banked SREC-II volume from the 2015 Compliance Filings, resulting in a baseline Compliance Obligation of 1,102,311 MWhs and a Minimum Standard of 2.2960%. These values will be increased to 1,169,357 MWhs and 2.4357%, respectively, if the SREC-II auction does not fully clear in the first two rounds.

Preliminary 2017 Compliance Obligation SREC-II Table 2

Additionally, the DOER calculated the preliminary 2017 SREC-II Compliance Obligation and Minimum Standard for load under contracts signed after May 8, 2016 – 1,496,188 MWhs and 3.1164%, respectively. These values will be increased to 1,563,234 MWhs and 3.2561% if the SREC-II auction does not fully clear in the first two rounds.

Preliminary 2017 Compliance Obligation SREC-II Table

The DOER also published a resource outlining its calculation of the preliminary SREC-II Minimum Standard.

Solar Credit Clearinghouse Auctions

The first rounds of the SREC-I and SREC-II Solar Credit Clearinghouse Auctions are scheduled for July 29, 2016. A second and third round will be held as needed the following week should these auctions not fully clear.

The DOER has also provided slight updates to the volumes of SRECs available in the Auctions: 1,896 in SREC-I and 67,046 in SREC-II.

SRECTrade will continue to monitor the proceedings of the Solar Credit Clearinghouse Auctions and will report the outcomes of the Auctions once the results become readily available.

Massachusetts SREC-II Emergency Regulation Filed: April 8, 2016

Posted April 11th, 2016 by SRECTrade.

On Friday, April 8, 2016 (the effective date), the Massachusetts Department of Energy Resources (MA DOER) announced it filed emergency regulation with the Secretary of State’s office. The regulation was submitted to address the current uncertainty in the solar industry and facilitate a smooth transition from SREC-II to the next incentive program. Although this emergency regulation is effective immediately, it can only remain in effect for 90 days pending a full DOER rule-making proceeding. Information on next steps in the emergency regulation process is still forthcoming, including public hearings and public comment submission deadlines.

Notably, the emergency regulation implements the following:

  • Extends SREC-II eligibility to all systems greater than 25 kW constructed by January 8, 2017; 9 months from the effective date
  • Extends SREC-II eligibility to all systems less than or equal to 25 kW interconnected by the start of the next incentive program
  • Implements compliance exemption for all electricity supply contracts signed within 30 days of the effective date
  • Ensures SREC-II will run through 2027

In regard to systems greater than 25 kW, the emergency regulation grants Statements of Qualification dated April 8, 2016, to all systems that have an existing Assurance of Qualification or that have submitted an application. The retention of granted Statements of Qualification is dependent on systems demonstrating (1) authorization to interconnect or (2) proof of construction to the DOER by January 8, 2017.

Reiterating the note above, in regard to systems less than or equal to 25 kW, all applications that demonstrate authorization to interconnect by the start of the next incentive program will be qualified under the SREC-II program.

In close, the DOER noted that development of the Commonwealth’s next solar energy incentive program is underway. Sustainable Energy Advantage, LLC (SEA) has been engaged to assist in conducting analysis in evaluation of the next program. Additionally, the DOER will work with market participants to solicit feedback as the program is designed and implemented.

SRECTrade will continue to monitor the status of the emergency regulation and provide updates regarding the future of Massachusetts’s next solar incentive program. We look forward to watching the state continue to structure competitive market based solutions, similar to those previously utilized, to continue its position as a national leader of deploying distributed solar technologies.